Projects Plan

First, thank you and our community for the overwhelming, 88.51% support of Proposition U! The District’s zero tax rate increase bond issue will generate $65 million for upgrades, repairs, renovations and reimagining of space districtwide.

Our Finance Department will sell the first round of bonds in early July, generating the funding we need to proceed with Phase I of the three-phase project list. Phase I projects are priority projects either related to safety and security or where there is an immediate academic, infrastructure or athletic need. Priority 2 Projects will fall into Phase II. Phase III includes the renovation of our high school's west wing (along Balson Ave.). 

Below, please see the exciting Phase I plans for our schools! Some of these projects will either take place or launch this summer with others occurring over the 2024-25 or 2025-26 school years. Project construction start - finish timelines are included in the Phase I project list below for each school.

Julia Goldstein Early Childhood Education Center

  • Multipurpose Room - Refresh our indoor play and learning space to encourage more interactive engagement (Summer 2024 - Fall 2024).
  • Secure Entry - Entrance will be reconfigured for greater safety and security (Summer 2024 - Summer 2024).
  • Premise ID - In late 2023, the City of University City passed an ordinance requiring a standardized way-finding system for first responder entry and guidance in the event of an emergency. This system involves adding signage to windows, to both interior and exterior doors, to specific walls within rooms, and to walls at certain sections of corridors (Summer 2024 - Fall 2024).
  • Video Cameras - Upgrade of cameras for improved security (Fall 2024 - Fall 2024). 
  • Parking Lot Upgrades - Asphalt areas will receive much-needed attention (Summer 2024 - Summer 2024).
  • Outdoor Public Address System - Facilitates communication with students and staff while learning or playing outside the building (Spring 2025 - Summer 2025). 
  • Hot Water Pump - Replace the hot water pump (Summer 2024 - Fall 2024). 
  • Roof Repair - Addressing immediate roof needs (Summer 2024 - Fall 2024).

Barbara C. Jordan Elementary School

  • Secure Entry - Entrance will be reconfigured for greater safety and security (Summer 2024 - Summer 2024). 
  • Premise ID - In late 2023, the City of University City passed an ordinance requiring a standardized way-finding system for first responder entry and guidance in the event of an emergency. This system involves adding signage to windows, to both interior and exterior doors, to specific walls within rooms, and to walls at certain sections of corridors (Summer 2024 - Fall 2024).
  • Video Cameras - Upgrade of cameras for improved security (Fall 2024 - Fall 2024). 
  • Outdoor Public Address System - Facilitates communication with students and staff while learning or playing outside the building (Spring 2025 - Summer 2025). 
  • Outdoor Learning Space - Reimagining additional play and learning spaces (Summer 2025 - Summer 2025).

Flynn Park Elementary School

  • Gymnasium - Air conditioning in our gymnasium will be a welcomed relief! (Summer 2024 - Fall 2024)
  • Data Network Closet - Upgrades to location of equipment (Summer 2024 - Fall 2024).
  • Secure Entry - Entrance will be reconfigured for greater safety and security (Fall 2024 - Spring 2025). 
  • Premise ID - In late 2023, the City of University City passed an ordinance requiring a standardized way-finding system for first responder entry and guidance in the event of an emergency. This system involves adding signage to windows, to both interior and exterior doors, to specific walls within rooms, and to walls at certain sections of corridors (Summer 2024 - Fall 2024).
  • Video Cameras - Upgrade of cameras for improved security (Fall 2024 - Fall 2024). 
  • Outdoor Public Address System - Facilitates communication with students and staff while learning or playing outside the building (Spring 2025 - Summer 2025). 
  • Outdoor Learning Space - Reimagining additional play and learning spaces (Summer 2025 - Summer 2025).
  • Roof Repair - Addressing immediate roof needs (Summer 2024 - Fall 2024).

Jackson Park Elementary School

  • Secure Entry - Entrance will be reconfigured for greater safety and security (Fall 2024 - Spring 2025). 
  • Playground - Replace equipment for safety and accessibility (Summer 2024 - Summer 2024).
  • Premise ID - In late 2023, the City of University City passed an ordinance requiring a standardized way-finding system for first responder entry and guidance in the event of an emergency. This system involves adding signage to windows, to both interior and exterior doors, to specific walls within rooms, and to walls at certain sections of corridors (Summer 2024 - Fall 2024).
  • Video Cameras - Installation of cameras for improved security (Fall 2024 - Fall 2024). 
  • Parking Lot Upgrades - Asphalt areas will receive much-needed attention (Summer 2024 - Summer 2025).
  • Data Network Closet - Upgrades to location of equipment (Summer 2024 - Fall 2024).
  • Flooring - Repair and replacement of targeted areas (Summer 2024 - Summer 2025).
  • Outdoor Public Address System - Facilitates communication with students and staff while learning or playing outside the building (Spring 2025 - Summer 2025). 
  • Outdoor Learning Space - Reimagining additional play and learning spaces (Summer 2025 - Summer 2025).
  • Roof Repair - Addressing immediate roof needs (Summer 2024 - Fall 2024)

Pershing Elementary School

  • Playground - Replace equipment for safety and accessibility (Summer 2024 - Summer 2024).
  • Secure Entry - Entrance will be reconfigured for greater safety and security (Summer 2024 - Summer 2024). 
  • Premise ID - In late 2023, the City of University City passed an ordinance requiring a standardized way-finding system for first responder entry and guidance in the event of an emergency. This system involves adding signage to windows, to both interior and exterior doors, to specific walls within rooms, and to walls at certain sections of corridors (Summer 2024 - Fall 2024).
  • Video Cameras - Installation of cameras for improved security (Fall 2024 - Fall 2024). 
  • Parking Lot Upgrades - Asphalt areas will receive much-needed attention (Summer 2024 - Summer 2024).
  • Outdoor Public Address System - Facilitates communication with students and staff while learning or playing outside the building (Spring 2025 - Summer 2025). 
  • Outdoor Learning Space - Reimagining additional play and learning spaces (Summer 2025 - Summer 2025).

Brittany Woods Middle School

  • Office - Entrance will be reconfigured for greater safety, security and functionality (Summer 2024 - Fall 2024). 
  • Premise ID - In late 2023, the City of University City passed an ordinance requiring a standardized way-finding system for first responder entry and guidance in the event of an emergency. This system involves adding signage to windows, to both interior and exterior doors, to specific walls within rooms, and to walls at certain sections of corridors (Summer 2024 - Fall 2024).
  • Outdoor Public Address System - Facilitates communication with students and staff while learning or playing outside the building (Spring 2025 - Summer 2025). 
  • Dance Studio - Replace the floor for better ergonomics (Summer 2024 - Fall 2024).
  • Theater - Replace and upgrade some of the lighting and audio-visual systems (Summer 2025 - Fall 2025).
  • Sustainability - Expand indoor/outdoor space for our award-winning Sustainability classrooms! (Summer 2024 - Fall 2024).
  • Secure Track Area - Enclosing the track and field area (Summer 2024 - Summer 2024).
  • Parking Lots - Repair of asphalt walking, driving and parking spaces (Summer 2024 - Summer 2024).
  • Broken Center Panels - Exterior building repair (Summer 2024 - Fall 2024).
  • Roof Repair - Addressing immediate roof needs (Summer 2024 - Fall 2024).

University City High School 

  • Premise ID - In late 2023, the City of University City passed an ordinance requiring a standardized way-finding system for first responder entry and guidance in the event of an emergency. This system involves adding signage to windows, to both interior and exterior doors, to specific walls within rooms, and to walls at certain sections of corridors (Summer 2024 - Fall 2024).
  • Video Cameras - Installation of cameras for improved security (Summer 2024 - Summer 2024).
  • Outdoor Public Address System - Facilitates communication with students and staff while learning or playing outside the building (Spring 2025 - Summer 2025). 
  • Parking Lots - Repair of asphalt walking, driving and parking spaces (Summer 2024 - Summer 2024).
  • Auditorium - Renovations to include the balcony that is presently unused and begin to upgrade the audio-visual equipment (Fall 2024 - Summer 2025). 
  • Multi-purpose Athletic Field - Significant upgrade to include turf, lights and stadium upgrades that support several different sports (Summer 2024 - Summer 2026).
  • Sustainability - Expand and create innovative spaces for our sustainability classrooms (Summer 2024 - Fall 2024).
  • Jackson Park Athletic Field Renovation - Significant field upgrades to support our athletic teams (Summer 2025 - Spring 2026).
  • Roof Repair - Addressing immediate roof needs (Summer 2024 - Fall 2024).
  • Locker Room - Upgrades to locker room facilities (Summer 2024 - Summer 2026).